PORTLAND – A California company has notified Oregon officials it plans a wind farm covering 32,000 acres with 300 turbines.
The Shepherds Flat Wind Farm would be the largest in the Columbia River Gorge. It would generate 750 megawatts of electricity, enough to power about 188,000 homes.
The developer, LifeLine Development Group of Sacramento, is a newcomer to the wind-energy boom in the gorge and hasn’t developed any wind farms.
It was formed expressly for Shepherds Flat, said Patricia Pilz, LifeLine’s development vice president.
She declined to identify corporate principals, except to say most were from California with strong backgrounds in wind energy.
LifeLine told the Oregon Department of Energy last week of its plans. A detailed application is due in September. A review by the state agency is required when wind projects exceed 105 megawatts.
“This is the largest one we’ve seen,” said Diana Enright of the department.
LifeLine would be built in phases of 250 megawatts each, Pilz said.
The turbines, each with a 2.5-megawatt capacity, would hook into transmission lines leading to a Bonneville Power Administration interconnection that would take the power to population centers to the west.
The first phase of the project wouldn’t be completed until 2008, when BPA expects to improve a substation to accommodate the new power generation.
The site is near the Columbia River town Arlington in Gilliam and Morrow counties.
Clint Krebs owns most of the land, where he runs sheep and cattle. He’s been advocating such a project for years.