Little Falls Reservoir drawdown planned, Avista says
RIVERS -- Avista is completing spill gate maintenance work at its Little Falls Dam, which requires the Little Falls Reservoir to be drawn down over the next few months.
This work will begin on Monday, July 11, and is scheduled to be completed within 12 weeks.
Work requires the reservoir to be lowered as much as 6 feet beginning Sunday, July 10, through Monday afternoon.